|
Release 5.02a: 2 December
2002
|
This release has been reassessed and approved by BRE as it
incorporates a change affecting SAP Ratings. Changes:
-
You can now enter a solar panel area when the main means of heating DHW
is an immersion heater: previously you could only do this when there was a
cylinder heated by a boiler
-
The Rf insulation limit for ground floors with overall insulation has
been raised from 2.5 to 3.0 - the additional figures have been calculated using
the same formulae used to calculate the original Table C1. Where the insulation
provides a greater thermal resistance than this, a note is now added stating
that the excess has been ignored
-
The Building Summary report now shows the total opening areas (with
metal/non-metal split except in NI)
-
The compliance reports now show more clearly which set of provisions
are being used
-
A correction has been made re checking of non-domestic buildings for
compliance with the Part J (Scotland) Elemental requirements - previously
we made separate checks on the average U-values of doors and windows and of
rooflights: now the average U-values of all metal and non-metal framed openings
are checked. The layout of the non-dwelling Elemental report has also been
revised.
|
Release 5.01a:
21 November 2002
|
-
Non domestic buildings in England, Wales and Scotland:
ERROR CORRECTED - PLEASE NOTE: When
checking for compliance with the L2 Calculation & Part J Heat Loss methods:
we made a mistake in applying the rule (which did apply before this year's
change, and still applies in NI) that where the actual building has opening
areas less than that allowed by the Elemental Method, such lower areas should
be used when calculating the heat loss of the notional building. This is not
correct: the notional building now has the full area of window and rooflight
openings regardless of what is in the actual building, so in some cases a
building could be shown as not complying when it did. However, where the actual
opening area is less than that allowed by the Elemental Method you are given a
tolerance of just 0.02 for the average U-value of the solid elements, so you
cannot (say) reduce window areas to allow a poorer level of wall insulation.
You can, though, reduce the window or rooflight area and use glazing with a
worse U-value than required by the Elemental Method - though note the
requirement to provide adequate daylighting - or use this method to allow one
wall area to have a much higher U-value, compensated for by another wall area
with a better than required U-value. For a more detailed discussion see our
web site
-
You can now define where the INI file(s) used to store the program
settings are located, a change which has been requested by a number of network
administrators.
-
The required minimum efficiency for oil combis when checking against
the Elemental Method has been corrected to 82%
-
Where ground floor insulation provides a thermal resistance higher than
that shown in tables C1-C3 the excess is ignored; a note to this effect is now
added to the U-value calculation where this applies.
-
The Construction Library materials list now shows the
resistance/resistivity of the material
-
The User Setup dialog now lets you delete unwanted page heading
templates - if you also have SuperBeam and/or ProSteel installed, note that the
same heading templates are shared by all three.
-
A new 'Information' option has been added to the Configuration menu.
This displays information about the program including licence details and file
names and locations.
-
There is a pending change (which has to be approved by BRE before we
make it public) to allow solar panels to be used in conjunction with cylinders
heated by immersion heaters - currently this is (incorrectly) a disallowed
combination.
|
Release 5.00e: 12 August
2002
|
The key change is that the provisions of
N.I.
Technical Booklet F 1998 edition have now been implemented in the program
and are applied when you select 'N.I.' in the Building Details dialog. There
are now two editions of the manual: one for users in England, Wales and
Scotland, the other for users in Northern Ireland
-
The Elemental Report for extensions has been enhanced to show the floor
area and (in E&W) whether or not the extension meets the alternative way of
showing compliance in §1.12 (trade-off U-values). For buildings being
checked in accordance with Part L (E&W), the Elemental U-value for
roofs with insulation between rafters in extensions has been changed from 0.2
to 0.3 (though note that this relaxation technically only applies to rooms in
roofs)
-
The Elemental Report for extensions no longer shows the heating system
efficiency in E&W as our reading of Part L is that this is not a material
factor in determining compliance. In Scotland the heating system type and
efficiency determines the U-values to be used.
-
A bug has been fixed that could cause an inaccurate calculation of
U-values for newly added constructions containing two or three alternate heat
paths
-
A bug has been fixed that gave an incorrect value for permissible
rooflight areas in non-domestic buildings where the avereage U-value of the
rooflights was more than the Elemental standard when checking for compliance
with the Elemental Method
-
The Ground Floor edit dialog now accepts floor P/A ratios down to 0.05
instead of 0.10 which enables the U-values of much larger floors to be
calculated (for example the previous limit for a 40m wide floor was a 40m
length; there is now no limit)
-
The U-values of solid floors with overall insulation are now calculated
using Appendix C rather than by adding the thermal resistance of the insulation
to that of the uninsulated floor: this may give a slightly worse U-value than
before
-
Cutting a wall from the Project Manager didn't force a recalculation -
fixed
-
The Element of Construction edit dialog didn't handle wider than normal
scroll bars - fixed
-
The presentation of several reports has been improved
|
Release 5.00d:
23 April 2002
|
The main change is a completely revised way of handling
opening areas when checking buildings using the Elemental and Calculation/Heat
Loss methods. For a full explanation click here
The floor edit dialog now adds a helper button which displays the
semi-exposed element additional thermal resistance dialog (as for semi-exposed
walls)
|
Release 5.00c:
16 April 2002
limited distribution only
|
-
When checking a dwelling against Part J (Scottish regulations)
Elemental requirements, the dwelling would be shown as failing if the heating
system was not one of those listed in Table 2. This was not correct: in
such cases the lower U-value limits in Table 1 Column B apply. The
necessary change has been made.
-
When checking against the Elemental Method requirements, the
calculation for the allowable door and window opening areas was incorrect, and
gave too low a permissible area: the correct calculation (for dwellings) is
permissible area of openings x (Elemental Method openings U-value-Elemental
Method wall U-value)/(actual average U-value of openings - Elemental Method
wall U-value). The calculation in 5.00a and 5.00b left out the last term.
|
Release 5.00b:
12 April 2002
|
This fixes two small bugs that have just shown up:
-
The roof edit dialog would not accept an overridden U-value - fixed
-
The bitmaps in the help file were missing (note that the help file text
is taken from SuperHeat 4 and has only been partly revised)
|
|
|
|
Release 5.00a:
28 March 2002
|
Fully revised to check buildings against the 2002
Part L and Part J requirements and produce SAP-2001 ratings.
(Northern Ireland version will be available at the end of June 2002). Do NOT
install SuperHeat 5 alongside SuperHeat 4.00a-4.57a inc. (all
SuperHeat 4 users who upgrade have been or will be sent 4.57b or 4.57c).
|
Release 4.57c:
1 March 2002
|
This incorporates minor internal changes which reduce the
memory used by the program.
Enrolled in our web update scheme?: If you are using 4.57b with no problems
there is no particular reason to download this update. Users of earlier
versions are advised to do so (you will need to have entered an activation key
ending in 202 or greater to do so). If your activation key was sent with a
serial number starting with 456 please request a new serial number starting
with 457 and its corresponding activation key
|
Release 4.57b:
26 February 2002
|
Minor change because of a problem with reading the new
format SEDBUK database which did not show up when using the test file
previously supplied to us.
|
Release 4.57a:
13 February 2002
|
-
In support of the new SAP2001 rating the SEDBUK database format is
being changed and SuperBeam 4.57 will handle the new format (which will be used
from 1 March 2002); SuperHeat 4.55 and 4.56 will not.
-
SuperHeat 4.57 will read SuperHeat 5 building files, though some
details may be changed (for example some of the heating control options in
SAP2001/SuperHeat 5 are not included in SAP1998/SuperHeat 4). This
facility is intended for use in exceptional circumstances only, for example
when you have started a job in SuperHeat 5 (with SAP 2001) and you
need to produce a SAP 1998 rating
-
SuperHeat 5 generates construction library files contains additional
data relating to U-value corrections. SuperHeat 4.57 does not use this data but
preserves it if you re-save the Construction Library (i.e. you can use the same
Construction Library with SuperHeat 4.57 and SuperHeat 5). Earlier
releases will throw up error messages if you try and use a Construction Library
file generated by SuperHeat 5 and will drop the additional data.
- Top -
SuperHeat support page and 2003
changes 2001 (and earlier)
changes
|